Karachi Metropolitan Corporation started a construction of dual flyovers during a Korangi Crossing to assistance palliate trade Flow. PHOTO: ATHAR KHAN/EXPRESS
KARACHI: The construction of a Korangi Crossing flyovers in front of Indus Hospital came to a harsh hindrance as a Sindh supervision unsuccessful to approve a revised PC-1 of a devise with updated costs.
In Nov final year, a Karachi Metropolitan Corporation (KMC) started a construction of dual flyovers during a Korangi Crossing to assistance palliate trade flow. Flyover I, on a highway from KPT Interchange towards Ibrahim Hyderi, is two-way and already underneath construction.
However, a predestine of Flyover II, in front of a Indus Hospital on a highway entrance from Nasir Jump to a one heading to KPT Interchange, hangs in a balance. The construction of a dual flyovers is partial of one project.
The ground-breaking rite of a dual flyovers was achieved by former Chief Minister Qaim Ali Shah, pronounced an central of a project’s contractor, Shamsher Khan and Co, requesting anonymity.
Initially, an underpass was to be assembled during a Korangi Crossing though due to a participation of vital application lines a thought was scrapped and a revised PC-1 of a flyover has nonetheless to be approved, combined a official.
The central explained that a pier of flyover we has been finished and they only need to launch a garters, that will take roughly a month. However, according to him, due to a check in a revised PC-1 of a project, a construction of Flyover we has also been halted.
There is a camber of Flyover we over that Flyover II will be constructed, he said. For this reason, he explained, it is required for them to start a pier work of Flyover II and place a garters during a intersecting camber so that during slightest Flyover we can be completed.
On a other hand, an operative of KMC during a site, Muhammad Tahir, pronounced that a PC-1 has roughly been authorized by a Sindh supervision and shortly a pier work of Flyover II will start.
The pier machines, that a executive will rent, are now being used for a Green Line Bus Rapid Transit devise in a city, due to that a construction will be delayed, explained Tahir.
Extra-tension wires
Apart from that, a K-Electric’s additional high-tension wires of 132,000 kilovolt, that are potentially one of a reasons of a project’s delay, will be relocated, pronounced Tahir.
Meanwhile, a Shamsher Khan and Co’s central pronounced that a K-Electric’s determination for a relocation of their application lines was Rs7.3 million. Due to this, he said, they due to them to govern a relocation themselves and a K-Electric will have to place subterraneous cables instead, that has reduced a cost.
Indus Hospital’s reservations
The Indus Hospital, that is in enlargement mode, has a possess set of reservations with a construction of flyover II.
Earlier, one of a first members of a hospital, Dr Akhtar Aziz, had told The Express Tribune that they devise to enhance a trickery from 150 beds to 1,800 beds. Due to this, he said, a sanatorium will accept 10 times some-more patients and ambulances than they customarily did.
According to him, with a construction of a flyover, a three-lane highway in front of a sanatorium will spin into a two-lane one as a flyover’s ramp will be assembled on one lane.
Indus Hospital asked a KMC to arrange segregated U-turns for ambulances rushing towards a sanatorium and a low-height underpass for pedestrians as good as special train ramps for open buses to forestall a overload of traffic.
The arch executive officer of a hospital, Dr Abdul Bari Khan, pronounced that a KMC has now concluded to their design, including a U-turns.
Published in The Express Tribune, Oct 17th, 2016.